New 132 kV cable between Capital District 400/132kV Grid station, WATH 132/22/11kV Substation and MCAA 132/11kV Substation
Project Title
Abu Dhabi
Category
Installation
Location
Abu Dhabi
On Site
Pipe Diameter: 5ways(4x225mm + 1x90mm OD)
Pipe Material: High Density Polyethylene Pipe (HDPE) SDR 17
Year: 2022
Number of Crossings: 29 crossing completed
Total length: Completed 1,420 approximately